Eagle Creek Restoration Project, Richland, Oregon (2008 - 2009)
QCI provided surveying, engineering design, and construction management services on a project to replace two existing diversion structures on Eagle Creek with fish passable rock weirs. Irrigation diversion rates at the two locations were 22 and 41 cubic feet per second, with river flows varying from a low of about 100 cubic feet per second to over 4,000 cubic feet per second. One of the sites had a maximum elevation drop of nearly six feet across the existing structure, which was accommodated with a number of grade control weirs to maintain the water surface elevations necessary to provide adequate water deliveries over a wide range of flow rates. This project also provided for approximately 1,400 linear feet of bank stabilization. QCI personnel also coordinated with the local water users and adjacent landowners to obtain their input with respect to irrigation operations and project access for construction.
Clear Creek Restoration Project, Halfway, Oregon (2008 - Present)
QCI personnel are working with representatives of the U.S. Fish & Wildlife Service and the Baker County Association of Conservation Districts to develop designs to replace four existing irrigation diversion structures on Clear Creek with rock weir structures to allow for improved fish passage. The existing improvised diversion structures are a combination of steel, broken concrete, and gravel push-up dams. Design flow ranges from 2.5 to 11 cubic feet per second. Construction is anticipated for fall of 2010, depending upon funding.
Spread Creek Fish Passage Improvement Project, Teton National Park, Wyoming (2008 – Present)
QCI is working in conjunction with Trout Unlimited to provide for improved fish passage at an existing concrete diversion structure on Spread Creek. The existing concrete diversion structure is approximately nine feet high and 120 feet long with a four to six foot head differential between the upstream and downstream sides. The project proposal is to remove the existing structure and replace it with a series of rock weirs to maintain a maximum irrigation delivery rate of 60 cubic feet per second. The project includes the construction of a new headgate structure, measurement devices, and 1,100 linear feet of pipeline. A segment of the pipeline operates as an inverted siphon to facilitate an underground crossing of Spread Creek.
Burnett Diversion Fish Passage Project, Mackay, Idaho (2009 - 2010)
Working with Trout Unlimited, QCI has developed a plan to provide whitefish passage at an existing concrete irrigation diversion structure on the Big Lost River near Mackay, Idaho. The existing structure created an approximately six-foot vertical barrier to upstream fish passage. The project design utilizes a natural rock ramp/fishway incorporated into the existing diversion structure, allowing the structure to be retained.
Anadromous Screening Program, Idaho Department of Fish & Game, Upper Salmon Basin, Idaho (1995 – Present)
Working with Idaho Department of Fish & Game engineers, Quadrant Consulting employees have designed approximately 40 screening facilities meeting NOAA Fisheries criteria for threatened and endangered anadromous stocks in the Upper Salmon River Basin. Designs have also included culverts, pipelines, roads, diversion structures, and an Obermeir Weir. Typical designs include incorporating concrete structures into a site grading plan, design of a bypass structure, and inclusion of miscellaneous appurtenances into a facility designed to continue delivery of historical irrigation flows.
Lindsey Lateral Reconstruction, Boise, Idaho (2004 - Present)
QCI has worked with the board members and water users of the Lindsey Lateral Water Users Association (composed of approximately 390 landowners) to complete a feasibility assessment, conceptual design, and cost estimate to repair and upgrade an approximately 23,000 linear foot gravity lateral system in urban Boise, Idaho. Both gravity and pressurized options are being reviewed.
Boise City Canal Reconstruction, Boise, Idaho (2004 - 2005)
QCI worked with Boise City Canal Company personnel to develop a project scope, obtain project funding, coordinate with public agencies (Boise City, the Ada County Highway District, and the Capital City Development Corporation), and complete civil design drawings to reconstruct or slip line over 900 linear feet of main line canal with a design capacity of approximately 50 cubic feet per second. The slip line portion of this project was located beneath the Basque Block in downtown Boise. The design of this section was conceived to allow the reconstruction of the canal without disturbing the existing street improvements or disrupt access to the adjacent businesses.
NRCS Oregon IDIQ, Portland, Oregon, (2005)
QCI provided surveying services and assisted with site irrigation planning, civil design, and preparation of construction documents for two irrigation projects located near Ontario and Vale, Oregon. One project included a 25 horsepower pump station and over 5,000 linear feet of pressurized mainline allowing the conversion of approximately 55 acres of land from flood irrigation to sprinkler irrigation. The other project included the rehabilitation of an existing storage pond, a 25 horsepower pump station, approximately 2,000 linear feet of pressurized mainline, and allowed for the conversion of approximately 30 acres of land from flood irrigation to sprinkler irrigation.
Little Morgan Creek Reconnection, May, Idaho (2003)
QCI served as a principal member of the design team on a multi-agency project involving numerous private landowner interests that was sponsored by the Custer Soil and Water Conservation District and funded by the Bonneville Power Administration to reconnect Little Morgan Creek to the Pahsimeroi River. QCI staff completed the design for a 12,000 linear foot pipeline with over 400 vertical feet of elevation change, provided surveying services, and completed a comprehensive water rights review for the project. QCI was also involved in public forums for the project, and along with other team members met with individual landowners on numerous occasions.
Two Ocean Creek Culvert Fish Passage, Teton National Park, Wyoming (2003)
QCI provided engineering design services on a project to obtain seasonal fish passage for native Snake River Cutthroat Trout through an existing 36-foot long concrete box culvert on Two Ocean Creek in Teton National Park. The design incorporated rock weirs downstream of the culvert to effectively reduce water velocities through the culvert to increase the opportunity for fish passage.