boise river flood control district 10
Location
Date |
Star, Idaho
1998 |
Beginning in the fall of 1998, Quadrant Consulting worked closely with Boise River Flood Control District personnel to obtain Stream Channel Alteration and 404 Permits from the Idaho Department of Water Resources, Idaho Department of Lands, and the US Army Corps of Engineers, respectively, for projects along approximately a 30 mile stretch of the lower Boise River to implement erosion control and channel remediation projects. The intent of these projects has been to protect private property along the river from erosion damage during high flow conditions while protecting or improving wildlife habitat within the riparian areas. On this project, Quadrant employees, including Nick, Ricardo, and Steve, have coordinated with and received input from representatives of the Idaho Department of Water Resources, US Army Corps of Engineers, Idaho Department of Fish and Game, Idaho Department of Lands, and the Idaho Department of Environmental Quality.