Lemhi big springs creek bridge replacement
Location
Date Cost |
Eagle Valley, Idaho
2008 $400,000 |
Quadrant was assigned the task of conducting an engineering analysis on the bridge that was used to access fish screens. Stapley Engineering was brought in to inspect the existing bridge, measure components, spans, ties, piers and other appurtenances. The analysis was followed up with recommendations concerning structural integrity, retrofits and a replacement bridge.